STAGE - 1
-
Select the style and location
-
Mortgage approval
-
Blueprints approval
-
Architectural approval
-
Building permit
STAGE - 2
-
Staking the site
-
Excavation
-
Weeping tile
-
Pouring footings and basement walls
-
Backfilling
STAGE - 3
-
Framing
-
Roofing
-
Rough in for vacuum, electrical, plumbing, heating, etc
-
Installation of gas line
-
Installation for electrical meter
-
City inspection for framing, electrical, plumbing, etc
-
Siding, soffit & fascia
STAGE - 4
-
Insulation
-
Inspection for insulation
-
Drywall & taping
-
Texturing
-
Painting
-
Kitchen cabinets
-
Countertops
-
Electrical fixtures
-
Tiles and hardwood
-
Carpet
STAGE - 5
-
Paint touch ups
-
Final cleaning, interior and exterior
-
Final city inspection
-
Rough grading (seasonal)
-
Victory quality assurance inspection
-
Pre-occupancy inspection
-
Final legal documents
-
Keys are handed over to the owner on the occupancy day